Bharat Petroleum Corporation Ltd Guidance Report - SOIC x StockScans Report

as of Oct 2026

  1. Gas business capex - additional ₹2,500 crore in FY25 Partial - After investing ₹1,920 crore in the Gas business in FY24, management planned an additional ₹2,500 crore in FY25, focused on expanding the CGD network. FY25 CGD capex came in at ₹2,283 crore, 91% of the ₹2,500 crore plan.
  2. CBG blending - tied up with 14 CBG manufacturers to meet obligations from FY26 Delivered - Management tied up with 14 CBG manufacturers for sustainable growth and to meet CBG blending obligations from FY26. CBG blending reached 6.5% in H1 FY27, more than double the 3% mandated target, with CBG retailing at 41 outlets since FY23.
  3. Consolidated refining capacity - from 35.3 MMTPA to 45 MMTPA On track - In the FY26 Annual Report, management said they were on track to enhance consolidated refining capacity from 35.3 MMTPA to 45 MMTPA, alongside preparations for a new greenfield refinery in Andhra Pradesh. Capacity stands at 35.3 MMTPA; the Bina expansion to 11 MMTPA is in execution and the 1 crore metric tonne AP refinery is in planning.
  4. Retail network expansion - \~3,000 outlets over three years On track - At the Q2 FY27 call, management guided retail network expansion of \~3,000 outlets over the next three years, 1,000 per year subject to land availability, with annual capex of ₹500 crore for 1,000 retail outlets. Retail outlets stood at 25,592 in Q2 FY27 vs 25,485 in Q1 FY27 and 25,323 at end FY26.
  5. Standalone peak debt-to-equity - around 1, returning to 0.4-0.45 after commissioning On track - At the Q2 FY27 call, management targeted standalone peak debt-to-equity of around 1, not to cross 1 significantly at peak capex, returning to 0.4-0.45 once projects are commissioned. Standalone gross borrowings were ₹15,246 crore as of 30 September 2026 with debt-to-equity at 0.16, vs 0.19 in Q1 FY27.
  6. FY '27-'28 capex - ₹40,000-45,000 crore Pending - At the Q2 FY27 call, management guided FY '27-'28 capex of ₹40,000 crore to ₹45,000 crore, with a baseline of ₹40,000 crore per cash flow projection. FY '27-'28 has not commenced, so there is no outcome evidence yet.
  7. FY27 capex - ₹25,000 crore On track - At the Q1 FY27 call, management reiterated full-year FY27 capex guidance of ₹25,000 crore as "unchanged"; by Q2 FY27 they flagged it may go up "maybe 5% to 10%" as projects are in full swing. H1 FY27 capex was ₹13,749 crore, including ₹9,300 crore in Q2, 55% of the ₹25,000 crore target.
  8. Bharat Gas Lite JEEP - expand to 100 additional cities by 15th August 2026 Delivered - At the Q1 FY27 call, management planned to expand Bharat Gas Lite JEEP to 100 additional cities across 24 states by 15th August 2026. Q2 FY27 disclosure confirms the Bharatgas Lite ZIP composite cylinder is available across India, bookable via the Hello BPCL app.
  9. Brazil project - first oil '30-'31, first gas '31-'32 On track - At the Q1 FY27 call, management guided Brazil project first oil expected '30-'31 and first gas '31-'32. An FPSO contract was signed with the operator in Q1 FY27, with expected reserve size \~88,000 barrels per day and BPCL holding 40%; the project is progressing in line with planned timelines after the May 2026 FPSO tender award.
  10. Mozambique future capex - $1.8 billion over next couple of years Pending - At the Q2 FY27 call, management guided Mozambique future capex commitments of $1.8 billion over "the next coming couple of years". Cumulative spend on Mozambique was $2.8 billion as of September 2026, with total project investment expected to reach \~$4.5-4.6 billion including exploration; no spend against the future commitment has been disclosed.
  11. Mozambique gas marketing - full 1 MMT SPA gas tied up in next 2-3 quarters On track - At the Q2 FY27 call, management expected to complete marketing tie-up of the full 1 MMT Mozambique SPA gas "in next two, three quarters". SPA is tied for 0.1 crore metric tonnes of Mozambique gas to India, with marketing begun in Q2 and some small customer tie-ups in place.
  12. Mozambique LNG - first gas by mid-2028 On track - At the Q1 FY27 call, management guided first gas expected in FY2029; by Q2 FY27 this was revised to mid-2028, "either June or July... They have declared June 20". The project reached 47% completion as of September 2026 with $2.8 billion spent, project financing concluded with an 8-9 banker consortium and force majeure removed.
  13. AP refinery project - environmental clearance by Q2 FY27, FID to board in Q2 FY27 On track - At the Q1 FY27 call, management expected MOEFCC environmental clearance by Q2 FY27; by Q2 FY27 they expected to take the FID to the board "in next two to three weeks". The board has approved a wholly owned subsidiary with initial authorized share capital up to ₹4,900 crore, \~4,700 acres of land registered and DFRs in final stages; EC receipt and board FID are yet to be confirmed.
  14. PRFCC project at Mumbai Refinery - commissioning September 2029 On track - The ₹14,200 crore Petro Resid Fluidized Catalytic Cracking Unit at Mumbai Refinery was announced with Q1 FY27 guidance of scheduled commissioning September 2029; by Q2 FY27 the September 2029 date stood with planned capex of around ₹1,500 crore for this year. Progress reached 9.2% as of Q2 FY27 with project cost ₹13,626 crore and ₹130 crore incurred till Q2, vs 7% complete at Q1.
  15. Lube Oil Blending and Filling Plant at Rasayani - completion June 2025 Partial - The Lube Oil Blending and Filling Plant at Rasayani, a resitement of the Wadilube plant approved at ₹423.39 crore, was scheduled for completion in June 2025. The plant was mechanically completed in December 2025 with Phase 1 commissioning, six months late, and the approved cost revised to ₹526.56 crore.
  16. CCKPL augmentation and Irugur-Devangonthi Phase 2 - completion August 2028 On track - Augmentation of CCKPL from 3.3 MMTPA to 7 MMTPA, plus the 16-inch Irugur-Devangonthi Pipeline Phase 2 and Palakkad POL Terminal at an estimated ₹1,130 crore, was scheduled for completion in August 2028. The project achieved overall progress of 34.1% as on 31 March 2026.
  17. Irugur-Devangonthi multiproduct pipeline - completion September 2026 Partial - The Irugur-Devangonthi multiproduct pipeline, 352 km at 3.5 MMTPA approved at ₹1,725 crore, was first scheduled for October 2025 and revised to September 2026. Physical progress was 81.6% as on 31 March 2026, and at Q2 FY27 management expected this long-delayed project, delayed \~7-8 years, to be completed by December-January.
  18. Rasayani POL and LOBS project - completion September 2026 Partial - The Rasayani POL and LOBS project, approved at ₹2,585 crore, was scheduled for completion by September 2026. Physical progress was 79.1% as on 31 March 2026, with Q1 FY27 noting POL and LOBS installations at Vashini progressing in line with plan; no completion disclosure appears as of Q2 FY27.
  19. SAF co-processing facility at Mumbai Refinery - Phase 1 by December 2026, Phase 2 by December 2027 On track - The SAF co-processing facility at Mumbai Refinery's KHT unit, approved at ₹677 crore, was scheduled for Phase 1 completion by December 2026 and Phase 2 by December 2027; at Q2 FY27 Phase 1, a revamp of the kerosene hydrotreater, was targeted for commissioning by January 2027. In October 2026, BPCL signed India's first co-processing licensing agreement for the project; no commissioning disclosure yet.
  20. Petrochemical Intensity Index - from 2.3% to 8% Pending - Management announced projects to raise the Petrochemical Intensity Index from 2.3% to 8% and expand petrochemical capacity by 2.4 MMT. No disclosure of the current index or progress toward 8% appears; the Bina and Kochi petrochemical projects are in execution.
  21. Polypropylene Project at Kochi - commissioning 2027 On track - The Polypropylene Project at Kochi Refinery was announced as on track for commissioning in 2027; at Q2 FY27 the schedule was October 2027. The project was 40% complete at Q1 FY27, reaching 55.10% by Q2 FY27 with approved capex ₹4,850 crore and ₹1,178 crore incurred.
  22. Ethylene Cracker Project at Bina - commissioning 2028 On track - The Ethylene Cracker Project at Bina, gross cost ₹49,000 crore alongside a brownfield refinery expansion from 7.80 MMTPA to 11 MMTPA, was announced with potential commissioning planned in 2028; at Q2 FY27 the mid-2028 schedule stood unchanged. Progress reached 40.2% by Q2 FY27 with approved cost ₹43,367 crore and cumulative capex ₹7,566 crore, vs 30.7% at Q1 with ₹30,000 crore committed.
  23. CGD - balance 210 of 448 CNG stations to be gas-charged in FY24 Pending - In FY23 reporting, management stated 448 CNG stations were mechanically commissioned, 238 gas-charged, with the balance to be gas-charged in the next financial year. FY24 and FY25 reporting confirm 671 and 840 stations mechanically commissioned, but gas-charging of the balance 210 is not specifically confirmed in the cited sources.
  24. CGD capital expenditure - ₹35,355 crore for 8 new GAs Pending - For the 8 new Geographical Areas secured in the 11 and 11A CGD Bidding Rounds, BPCL pegged capital expenditure of ₹35,355 crore. No cumulative capex against this commitment is disclosed; FY24 CGD capex was ₹1,920 crore and FY25 CGD capex ₹2,283 crore.
  25. CGD capital expenditure - ₹3,000 crore for FY 2023-24 Missed - BPCL earmarked ₹3,000 crore of capital expenditure for CGD in FY 2023-24. FY24 actual CGD capex was ₹1,920 crore, 64% of the plan, vs ₹1,343 crore in FY23.
  26. Green hydrogen in refineries - 10% by 2030 On track - Management set a target of 10% green hydrogen for all refineries by 2030, with internal studies indicating around 72 MT per day of hydrogen would be required, and a green hydrogen plant being implemented at Bina Refinery. The 20 MW Bina project was "aggressively underway" as of August 2023, and a 500 kW BARC-technology alkaline electrolyzer was commissioned at Cochin International Airport; no production volumes against the 10% target are disclosed.
  27. Renewable energy capacity - 1 GW by 2025, 10 GW by 2040 Partial - In the FY23 Annual Report, management set an ambition of 1 GW renewable energy capacity by 2025 and 10 GW by 2040, via organic and inorganic routes; a September 2024 announcement stated aggressive targets to build 2 GW, superseding the earlier ambition. As of FY24, five solar projects of 45.5 MW and two wind projects of 100 MW were under implementation; a 71 MWp Prayagraj solar project was commissioned in December 2025 and 100 MW secured in a Q1 FY27 Madhya Pradesh wind tender - \~170 MW disclosed against the 1 GW target, with the 10 GW by 2040 horizon open.
  28. Mumbai Refinery KHT project (1.5 MMTPA) - completion December 2022 Delivered - The Mumbai Refinery KHT project, 1.5 MMTPA at an approved cost of ₹667.15 crore, was scheduled for completion in December 2022, with physical progress at 83% as on 31 March 2022. The 1.5 MMTPA Kerosene Hydrotreater Unit at Mumbai Refinery was commissioned in FY23, meeting the deadline.
  29. BS-VI Motor Spirit Block Project (MSBP) at Kochi - completion March 2021 Delivered - The BS-VI Motor Spirit Block Project at Kochi Refinery, approved at ₹3,288.96 crore, was scheduled for completion in March 2021. Kochi Refinery had been producing BS-VI MS and HSD since November 2019, and the NHT unit of MSBP was commissioned in FY21, meeting the deadline and the April 2020 BS-VI mandate.
  30. Project Aspire - double profits from the 2021-22 baseline, up to ₹1.7 lakh crore capex over five years On track - In the FY24 Annual Report, management committed to Project Aspire targeting a doubling of profits from the 2021-22 baseline with capex of up to ₹1.7 lakh crore over five years, the initial phase of a multi-decade investment programme. FY26 consolidated PAT of ₹25,843 crore indicates the profit objective has been substantially surpassed, while capex incurred - FY25 ₹16,967 crore, FY26 ₹21,372 crore and H1 FY27 ₹13,749 crore, roughly ₹52,000 crore cumulatively - continues against the five-year commitment.