Chennai Petroleum Corporation Ltd Guidance Report - SOIC x StockScans Report

as of Jul 2026

  1. Retail outlet rollout - 300 licences, ₹400 cr capex over 2-3 years Pending - At the Q4 FY26 call, management discussed operational and financial performance, including record throughput and GRM of $13.75/bbl, but the cited pages contain no mention of retail outlets, licences, or a ₹400 cr capex plan. As of Q4 FY26, no evidence of licence acquisition, commissioning progress, or outlet count has been disclosed in the provided sources.
  2. Throughput guidance FY26 - higher than FY25 Delivered - At the Q4 FY25 call, management guided that for FY25-26, "you can expect a throughput which is higher than last year" because the shutdown impact in the current year was lower than in the previous year. FY26 crude throughput reached 11.71 MMT at 112% capacity utilisation, surpassing FY25 throughput of 10.45 MMT.
  3. LOBS Group II/III project - implementation in 2-3 years, 250 KTPA capacity, ₹1,600-1,700 cr On track - At the Q4 FY24 call, management stated the LOBS Grade 2/Grade 3 project would take 2-3 years to implement, with the proposal at "a very advanced stage on approval" by Q4 FY25 and detailed at Q4 FY26 as a ₹1,600 cr project adding 250 KTPA over 2-3 years. As of Q4 FY26, IOCL approval was received in May 2025, environmental clearance obtained, and pre-project activities completed, with the 31-month timeline implying mechanical completion around December 2027.
  4. Net-zero Scope 1 & 2 emissions - by 2046 On track - In the FY25 Annual Report, CPCL committed to achieving net-zero Scope 1 and Scope 2 emissions by 2046. FY25 Scope 1 & 2 emissions were \~2,429 KT CO₂ eq, down from 2.83 MMTCO₂e in FY24, with progress visible through reduced emissions, renewable energy installations, and RLNG substitution.
  5. Compressed Biogas (CBG) - production commencing by FY27 Pending - In the FY24 Annual Report, CPCL stated it is targeted to commence Compressed Biogas production by 2026-27. Our record holds no progress disclosure on CBG production, and the FY25 AR mentions a shift towards CBG by 2040 but provides no update on the FY27 commencement target.
  6. Green Hydrogen - 2 KTPA by FY27, scale up to 10 KTPA by 2030 Pending - In the FY24 Annual Report, CPCL stated it is planning to implement Green Hydrogen at 2 KTPA capacity by 2026-27 and subsequently scale up to 10 KTPA by 2030 as per capacity allocated by MoPNG. Our record holds no progress disclosure on Green Hydrogen implementation, and the FY25 AR mentions a shift towards Green Hydrogen by 2040 but provides no update on the 2 KTPA by FY27 target.
  7. Pharma Grade Hexane project - 35 TMTPA, commissioned with ISOM M&I shutdown in Q2 FY25 Delivered - In the FY24 Annual Report, CPCL stated the Pharma Grade Hexane production project at Manali Refinery was expected to be completed along with the forthcoming ISOM M&I shutdown in Q2 FY2024-25, targeting production of 35 TMTPA. Pharma Grade Hexane production of 35,000 MTPA was commissioned in August 2024 at a cost of ₹69.91 cr, the product was launched on 20th September 2024, and FY25 saw highest ever production at 29.8 TMT and despatch at 29.5 TMT.
  8. Cauvery Basin Refinery (CBRPL) - 9 MMTPA on stream within 39 months of CCEA approval Pending - At the Q4 FY24 call, management stated the CBRPL project would take 39 months from CCEA approval, revised from an earlier 45-month timeline, with project cost at ₹36,354 cr and CPCL's equity share at 25% or ₹3,000 cr. As of Q4 FY26, CCEA approval has not been received and the 39-month clock has not started, though pre-project activities are advanced with land 100% acquired, all four EPCMs awarded, and physical progress at \~9.8% as of Q4 FY24.