Hindustan Petroleum Corporation Ltd Guidance Report - SOIC x StockScans Report
as of Oct 2026
- HRRL Rajasthan refinery - 9 MMTPA greenfield & petchem, full capacity by Q3 FY27
On track - At the Q1 FY27 call, management guided HRRL to ramp to full capacity in Q3 FY27 with petchem ramp-up by end of FY27, reiterating at Q2 FY27. Commercial operation was declared on 22nd June 2026; CDU ran at \~60% utilization in Q1 and Q2 FY27 with two secondary units remaining, and petchem first units guided to Q4 FY27.
- HRRL financial restructuring - interest burden down ₹1,000 cr, equity calls in 1-2 quarters
On track - At the Q2 FY27 call, management guided further equity calls within one or two quarters to lower interest by ₹1,000 cr overall versus last year. The entire ₹45,000-50,000 cr HRRL debt was refinanced end of September 2026 at \~105 bps lower, worth \~₹470-500 cr a year, and ₹4,200-4,300 cr of subordinate loans converted to equity cut interest by \~₹350 cr.
- HRRL GRM - $20+ post SAED at full run rate, Q4 FY27
On track - At the Q2 FY27 call, management guided HRRL GRM of "20 plus in Q4" post SAED once high-sulfur crudes start, expected December. Q2 FY27 GRM was $12 post SAED on stop-start operations, and the first 18 days of October 2026 reached $16.1 post SAED on low-sulfur crude.
- Vizag RUF - full $2-3 per barrel uplift by March 2027
On track - At the Q2 FY27 call, management held guidance for the full RUF benefit of $2 to $3 per barrel uplift, "hopeful of getting there in March, or even before that". The unit is consistently running at 60-70% capacity and has touched close to $1 per barrel uplift in some periods, with October expected at $0.65-$0.7 uplift.
- Chhara LNG terminal - 15-20% utilization in H2 FY27, cash positive for the year
On track - At the Q2 FY27 call, management guided five to six cargoes in H2 FY27, giving about 15% to 20% utilization, with Chhara plus bulk gas purchases cash positive for the whole year. The terminal now works about 10 months a year, with two or three spot cargoes done in the last month including an opportunity cargo at a significant discount.
- HP Navya LPG - 5 cities by 31st July, 25 cities by 31st August, \~200-250 cities by Diwali
On track - At the Q1 FY27 call, management guided HP Navya LPG to five more cities by 31st July, 25 cities by 31st August, and \~200 to 250 cities by Diwali. HP Navya launched on 15th July 2026 with piloting through Swiggy in Bangalore and own-channel start in Mumbai, and HPCL is market leader in the Navya composite cylinder since day one.
- Digital RTO/APC - saturation of all units at both refineries by end FY27
On track - At the Q1 FY27 call, management guided digital RTO/APC saturation of all units at both refineries other than HRRL, reaffirming "we will complete it this year" at Q2 FY27. APC is commissioned in all units of VRMP and RTO across multiple units of Mumbai and Visakh refineries, delivering yield uplift of 0.4-0.5% where measurement has started.
- Supply self-sufficiency - own refineries plus JVs cover \~95% of requirement by end FY27
On track - At the Q1 FY27 call, management guided that by end of this year own refineries plus JVs would make HPCL almost self-sufficient, reiterated at Q2 FY27 with internal sources covering "95% of our requirement". Q1 FY27 HSD sourcing was \~50% own production, \~27% from JV HMEL and \~24% bought out, with all Rajasthan products now going toward HPCL's gap.
- Non-fuel business - additional contribution line on P&L by end of March 2027
On track - At the Q1 FY27 call, management said it was "very hopeful by end of this March" the non-fuel business would appear as an additional contribution line on the P&L. Non-fuel retail is now at about 10% of pan-India retail outlets, up from 5.5% at the beginning of the year, after FY25 non-fuel revenues surpassed ₹200 cr.
- Capex - annual target \~₹9,700 cr for FY27, expected to be lower
On track - At the Q1 FY27 call, management stated the annual capex target agreed with the Government of India is \~₹9,700 cr and expected capex to be lower to conserve cash. Q1 FY27 capex spent was about ₹1,700 cr, largely on turnarounds, equipment and catalyst.
- Samriddhi 2.0 - ₹1,500 cr run-rate and ₹1,000 cr accruals in FY27
On track - At the Q1 FY27 call, management reinitiated Samriddhi 2.0 with a target of ₹1,500 cr on a run-rate basis and ₹1,000 cr on accruals, reiterating at Q2 FY27 despite a start delayed to Q2. ₹327 cr accrued in Q2 FY27 results with a run-rate locked in of about ₹600-700 cr, after ₹1,691 cr delivered in FY26.
- CBG platform - 10-11 plants under government scheme, 5 under construction
On track - At the Q2 FY27 call, management stated about 10 or 11 CBG plants filed under the government scheme, five under construction and the next six likely to go, as part of "building a platform" around CBG. The 14 TPD Budaun plant has started commercial sale with FOM compliant with FCO norms, the 1.6 TPD Pathmeda plant commenced CBG sale, and the 16 TPD Eluru plant is ongoing.
- Green hydrogen purchase - 5 KTPA from OCIOR, delivery from 31st July 2028
Pending - In the FY26 annual report, management stated a Green H₂ Purchase Agreement signed 29 Jan 2026 with OCIOR Green Fuels Pvt Ltd for supply of 5 KTPA green hydrogen to Visakh Refinery on BOO basis. A PO was placed on OGFPL with scheduled delivery from 31st July 2028.
- Lube Modernisation and Bottom Upgradation Project - LOBS 475 to 764 KTPA, bitumen +487 KTPA
On track - In the FY26 annual report, management stated the Mumbai Refinery project will lift LOBS production from 475 KTPA to 764 KTPA (Group II+ and Group III) and increase bitumen production by \~487 KTPA. The project is progressing on schedule and has achieved key milestones, with no completion or capacity read yet in our record.
- HPCL Renewables and Green Energy Limited - wholly owned subsidiary operational
Delivered - At the Q3 FY25 PPT, management stated the wholly owned subsidiary 'HPCL Renewables and Green Energy Limited' is now operational for consolidation of green & renewable business opportunities. HPCL has incorporated HPCL Renewable & Green Energy Limited (HPRGE) as the dedicated platform for renewable power and emerging energy businesses.
- Capex allocation FY24-FY28 - 36% in renewables/biofuels/natural gas/alternate fuels/net zero, 12% in non-fuel & petchem
Pending - At the Q3 FY25 PPT, management guided capex FY24 to FY28 with 36% in Renewables, Biofuels, Natural Gas, Alternate Fuels & Net Zero and 12% in Non-Fuel & Petchem. FY25 total capex was ₹14,508 cr focused on refining and marketing infrastructure, and last five years' investments of ₹74,000 cr include ₹1,000 cr in biofuels & renewables, but no FY24-FY28 allocation breakdown is in our record.
- 2G Ethanol biorefinery at Bathinda - 100 KLPD
Pending - At the Q3 FY25 PPT, management listed the 100 KLPD 2G Ethanol bio-refinery at Bathinda, Punjab as ongoing at ₹1,421 cr, also listed in the July 2023 announcement. No completion or commissioning read is in our record; the HBL distillery expansion for grain-based feedstock is in progress.
- 2x+ jump in EBITDA levels by FY28
On track - At the Q3 FY25 PPT, management stated it is working towards a 2x+ jump in EBITDA levels by FY28. FY26 EBITDA was ₹33,182 cr, but TTM EBITDA stood at ₹9,135 cr as of the latest reported Q2 FY27 after Q1 FY27 losses, with Q2 FY27 standalone EBITDA of ₹9,822 cr versus a ₹14,816 cr loss in Q1.
- Refining capacity - 45.3 MMTPA by FY28
On track - At the Q3 FY25 PPT, management guided refining capacity to rise from 34.5 MMTPA to 45.3 MMTPA by 2027-28, via Visakh +1.3, HMEL +0.5 and HRRL +9 MMTPA. Visakh and Mumbai expansions are commissioned and HRRL declared commercial operation on 22nd June 2026 at \~60% utilization, while no read on the 11.8 MMTPA HMEL expansion is in our record.
- Chhara LNG terminal - 5 MMTPA commissioned
Delivered - At the Q3 FY25 PPT, management presented the 5 MMTPA LNG regasification terminal at Chhara (HPLNG Limited, 100% subsidiary) at a project cost of ₹4,792 cr, commissioned in January 2025, with operations guided for Q2 FY26 at the May 2025 announcement. The terminal was operational from February 01, 2025 with multiple cargoes offloaded and an ADNOC Trading term deal finalized in April 2025.
- Green hydrogen - 12,200 TPA at Visakh, 4,300 TPA at HRRL
On track - At the Q3 FY25 PPT, management planned a 12,200 TPA green hydrogen project at Visakh Refinery and a 4,300 TPA green hydrogen project at HRRL. A 370 TPA green hydrogen plant at Visakh Refinery is commissioned, and a Green H₂ Purchase Agreement signed 29 Jan 2026 with OCIOR Green Fuels covers 5 KTPA supply with delivery from 31st July 2028.
- Visakh RUF - commissioning slipped one quarter past Q2 FY26 guidance
Partial - At the May 2025 announcement, management guided the RUF at Visakh Refinery to commission in Q2 FY26, after pre-commissioning activities, OISD and PESO inspections were completed and PESO approval obtained in April 2025. Commissioning occurred in December 2025 - Q3 FY26 - the world's first and largest LC-MAX installation, converting \~93% of bottom-of-the-barrel residue.
- HMEL polymer capacity - \~2 MMTPA after Bathinda petchem complex
Delivered - At the FY20 annual report, management stated that after commissioning of the upcoming Bathinda petrochemical complex, polymer production capacity at HMEL was expected to increase to about 2 MMTPA. The 1.2 MMTPA dual feed cracker polymer addition project is completed, and FY26 HMEL polymer sales exceeded 2.27 MMT with ethylene at \~105% of design capacity.
- Pipeline expansion - ₹5,600 cr, capacity to over 41 MMTPA, network \~5,300 km
Partial - At the FY20 annual report, management guided ongoing pipeline expansion projects of about ₹5,600 cr to increase pipeline capacity to over 41 MMTPA and network length to about 5,300 km. FY26 pipeline network reached 5,440 km, exceeding the \~5,300 km target, with 873 km of new pipelines commissioned in FY26, while annual throughput of 25.54 MMT is below the 41 MMTPA capacity target.
- BS-VI fuel supply - all POL locations by 31st March 2020
Delivered - At the FY20 annual report, management committed to BS-VI fuel supply across all POL locations by 31st March 2020 to meet the government directive of leapfrogging from BS-IV to BS-VI norms. BS-VI migration was completed at all POL locations within FY 2019-20 timelines, with both Mumbai and Visakh refineries upgraded and rollout completed before the government timeframe.
- Mumbai Refinery Expansion - 7.5 to 9.5 MMTPA
Delivered - At the FY20 and FY21 annual reports, management stated the Mumbai Refinery Expansion Project aims to enhance capacity from 7.5 to 9.5 MMTPA, in advanced stage of execution. The expansion was commissioned at a project cost of ₹5,381 cr as of December 2024, and the Mumbai Refinery achieved its highest crude throughput of 10 MMT in FY26.
- Visakh Refinery Modernization Project - 8.3 to 15 MMTPA
Delivered - At the FY20 and FY21 annual reports, management stated VRMP aims to enhance Visakh Refinery capacity from 8.3 to 15 MMTPA, with Residue Upgradation Facilities in progress. VRMP was dedicated to the Nation at a project cost of ₹30,609 cr as of December 2024, the RUF commissioned in December 2025, and the refinery posted highest-ever annual crude throughput of 16.04 MMT at 107% capacity utilisation in FY26.
- HPCL Renewables and Green Energy Limited - wholly owned subsidiary operational
Delivered - At the Q3 FY25 PPT, management stated the wholly owned subsidiary 'HPCL Renewables and Green Energy Limited' is now operational for consolidation of green & renewable business opportunities. HPCL has incorporated HPCL Renewable & Green Energy Limited (HPRGE) as the dedicated platform for renewable power and emerging energy businesses.