Indian Oil Corporation Ltd Guidance Report - SOIC x StockScans Report

as of Nov 2026

  1. Mauritius G2G supply - 100% of MS, HSD and Jet A-1 for 5 years Pending - At the Q2 FY27 call, management stated Indian Oil will meet 100% of Mauritius's requirement of motor gas, gas oil (HSD) and Jet A-1 ATF on delivered basis for the next 5 years under a G2G framework, with a signed SPA with STC Mauritius. No read yet; the agreement was just signed.
  2. TerraClean EBITDA positive by FY29-30, debt-to-equity 75:25 Pending - At the Q2 FY27 call, management targeted TerraClean to turn EBITDA positive by FY29-30, with projects coming on ground from '28, '29, '30 and a 75:25 debt-to-equity ratio. TerraClean is in pre-project stage with connectivity approvals and land aggregation underway.
  3. Renewable capacity - 18 GW in 3-4 years, raised to 31 GW in 5 years On track - At the Q1 FY27 call, management targeted 18 GW renewable power in the next three to four years via Terra Clean; at Q2 FY27 this was raised to 31 GW "in another 5 years" via organic and inorganic routes. Installed capacity is 259.68 MW, with TerraClean connectivity approvals for 2.65 GW and the 2 GW NTPC JV expected within 5-6 months.
  4. Petchem intensity - 6.5% to 15%, \~₹1,00,000 crore capex over 5-6 years On track - At the Q1 FY27 call, management planned to raise petchem intensity from 6.5% to 15% with capex of around ₹1,00,000 crore over five to six years; at Q2 FY27 it noted board approvals of almost ₹10,000 crore for petchem/specialty projects in the past year. Approved projects including LAB, PX and PTA will add 5 MMTPA of capacity by March 2030; FY26 petchem sales were 3.4 MMT.
  5. Q2 FY27 LPG under-recovery - \~₹250 per cylinder Delivered - At the Q1 FY27 call, management expected LPG under-recovery of around ₹250 per cylinder during Q2, assuming the same Saudi CP continues. Actual Q2 FY27 under-recovery was ₹184/cylinder in September and ₹229/cylinder in October, at or below the guided level.
  6. SPRINT 2 - ₹2,000-2,500 crore savings over last year's achievement Pending - At the Q1 FY27 call, management said SPRINT 2, recently announced, is expected to deliver another ₹2,000-2,500 crore savings over and above last year. SPRINT saved almost ₹2,000 crore in the last financial year; no FY27 savings figure has been disclosed yet.
  7. Throughput - \~77 MMTPA in FY26-27, 85 in FY27-28, 90 in FY28-29 On track - At the Q1 FY27 call, management expected throughput of around 77 MMTPA in '26-'27, around 85 MMTPA in '27-'28 and 90 MMTPA in '28-'29. FY26 actual throughput was 75.5 MMT; Q1 FY27 delivered 19.2 MMT and Q2 FY27 18.1 MMT, an H1 run-rate consistent with \~77 MMTPA.
  8. Ethanol blending - 20% government target achieved "very comfortably" Delivered - At the Q1 FY27 call, management committed to achieve the government's ethanol blending target, currently 20%, saying new targets would be achieved "very comfortably". The 20% target was achieved in Q1 FY27, at par with other OMCs.
  9. Four MR vessels under MoPNG-Ministry of Shipping MoU On track - At the Q1 FY27 call, management said that under the MoPNG-Ministry of Shipping MoU (signed 19th September, non-binding), Indian Oil shall explore procuring four MR vessels to start with, with tenders already out. By Q2 FY27 the board had given go-ahead to buy a few vessels under ship ownership; IOC currently holds 3 crude oil and 9 LPG vessels on time charter.
  10. Panipat refinery expansion - 15 to 25 MMTPA, commissioning December 2026 On track - At the Q4 FY26 PPT, management guided the Panipat Refinery Expansion (15→25 MMTPA, gross approved cost ₹38,231 cr) for commissioning December 2026, reiterated at Q1 FY27; at Q2 FY27 commissioning remained "this financial year" with crude throughput starting 5-6 months after initial commissioning. Physical progress was 92.8% at 31 March 2026, 94% at Q1 FY27 and 95% at Q2 FY27, with no commissioning yet disclosed.
  11. Gujarat refinery expansion - 13.7 to 18 MMTPA, commissioning November 2026 On track - At the Q4 FY26 PPT, management guided the Gujarat Refinery Expansion (13.7→18 MMTPA, gross approved cost ₹18,936 cr) for commissioning November 2026 with progressive start from July 2025, reiterated at Q1 FY27; at Q2 FY27 commissioning remained "this financial year" with ramp-up 5-6 months after initial commissioning. Physical progress was 87.8% at 31 March 2026, 90% at Q1 FY27 and 90% at Q2 FY27, with no commissioning yet disclosed.
  12. Barauni refinery expansion - 6 to 9 MMTPA, commissioning August 2026 On track - At the Q4 FY26 PPT, management guided the Barauni Refinery Expansion (6→9 MMTPA, gross approved cost ₹18,113 cr) for commissioning August 2026, restated at Q1 FY27 to December 2026; at Q2 FY27 commissioning remained "this financial year" with gradual ramp-up over 5-6 months. Physical progress was 90.5% at 31 March 2026, 92% at Q1 FY27 and 92.5% at Q2 FY27, with no commissioning yet disclosed.
  13. PX-PTA Complex at Paradip - commissioning August 2026 Partial - At the Q4 FY26 PPT, management guided the PX-PTA Complex at Paradip Refinery (gross approved cost ₹13,805 cr) for commissioning August 2026. Physical progress was 93.5% at 31 March 2026 and 95% at Q1 FY27 with commissioning expected "in the next one month"; the complex was mechanically completed in September 2026 with commissioning activities in progress.
  14. Poly Butadiene Rubber Plant at Panipat - commissioning June 2026 On track - At the Q4 FY26 PPT, management guided the Poly Butadiene Rubber Plant at Panipat (gross approved cost ₹2,949 cr) for commissioning June 2026; at Q1 FY27 the date was restated to December 2026. Physical progress was 84.3% as of 31 March 2026, and no commissioning had been disclosed as of Q2 FY27.
  15. R&D Campus-II, Faridabad - commissioning October 2026 Pending - At the Q4 FY26 PPT, management guided the New R&D Campus-II, Faridabad (gross approved cost ₹3,220 cr) for commissioning October 2026. Physical progress was 64.9% as of 31 March 2026; no commissioning has been disclosed in Q1 FY27 or Q2 FY27 notes.
  16. FY26-27 capex target - ₹32,700 crore On track - At the Q4 FY26 PPT, management set the FY 2026-27 capex target at ₹32,700 crore, reiterated at Q1 FY27 and Q2 FY27 calls. Q1 FY27 capex was ₹6,461 crore and H1 FY27 capex ₹12,162 crore, a half-year run-rate below the annual target.
  17. Green hydrogen - 50% of consumption by 2030 On track - In the FY24 Annual Report, management aimed for 50% of hydrogen consumption to be green by 2030, with green hydrogen plants across all refineries. Construction of India's first large-scale 10 KTPA Green Hydrogen Plant at Panipat commenced after the LOA issued 26 June 2025; no percentage of green hydrogen consumption has been disclosed.
  18. Upstream integration ratio - 5% to 10% by 2030 (\~11 MMT) On track - In the FY23 Annual Report, management targeted raising the upstream integration ratio from 5% to 10% by 2030 (\~11 MMT), primarily via domestic assets plus overseas opportunities. FY23 upstream production was over 4 MMT of oil equivalent; FY26 saw commercial gas production commence from the CBM block in Jharkhand and first oil from the Jyoti-1 well in Gujarat.
  19. Petrochemical manufacturing volume - 8.2 MMTPA by 2026-27 Pending - In the FY23 Annual Report, management targeted 8.2 MMTPA of petrochemical manufacturing volume by 2026-27. FY26 petrochemical production was 3.4 MMT; no read is available on FY27 production volume.
  20. SAF Plant at Panipat - 86.8 TMTPA with LanzaJet On track - In the FY23 Annual Report, management planned an 86.8 TMTPA SAF Plant at Panipat with LanzaJet, to be ultimately vested in a JV Company, reiterated in FY24 and FY26 annual reports. Panipat Refinery became the first in India to receive ISCC CORSIA Certification for SAF production; no read yet on plant commissioning or production volume.
  21. Natural gas sales portfolio - 3-4x expansion by end of decade On track - In the FY24 Annual Report, management planned to expand its natural gas sales portfolio by three to four times by the end of the decade, via RLNG terminals, cross-country pipelines, CGD networks and LNG stations. FY26 natural gas sales were 7.09 MMT against FY24 gas sales of 6.5 MMT; no read on the baseline for the target.
  22. Natural gas pipeline network - \~3,700 km by adding \~2,400 km Pending - In the FY24 Annual Report, management stated the company is expanding its natural gas pipeline network to \~3,700 km by adding \~2,400 km to its current 1,300 km. The pipeline network spanned 20,009 km as of 31 March 2026, including over 1,300 km of natural gas pipelines; no specific read on natural gas length.
  23. Ennore LNG Terminal - capacity 5 to 10 MMTPA Pending - In the FY24 Annual Report, management planned to expand Ennore LNG Terminal capacity from 5 MMTPA to 10 MMTPA. IndianOil LNG Pvt. Ltd. (45% JV) owns and operates the 5 MMTPA terminal at Kamarajar Port, Ennore; no read on expansion progress.
  24. CGD network - 49 GAs across the country Delivered - In the FY24 Annual Report, management stated the company is developing a CGD network in 49 GAs awarded through PNGRB's bidding rounds. Presence in 49 GAs and 112 districts across 21 states/UTs was in place as of FY23; FY26 saw CGD turn EBITDA positive, with standalone CGD contributing ₹90 crore to PBT in Q2 FY27.
  25. 30 CBG plants nationwide "this year" (FY24) Delivered - In the FY24 Annual Report, management planned to set up 30 CBG plants nationwide "this year". 8 CBG plants were commissioned during FY24, taking the tally to 31; a total of 49 CBG plants stood established as of 31 March 2026.
  26. Butyl Acrylate plant at Gujarat Refinery - commissioning 2024-25 Partial - In the FY24 Annual Report, management scheduled the Butyl Acrylate plant at Gujarat Refinery for commissioning in 2024-25. In FY26 the acrylic acid/butyl acrylate/Normal Butanol project was commissioned, marking entry into high-value petrochemicals, with Butyl Acrylate imports declining 23% post-commissioning.
  27. Praj Industries JV - 50:50 for SAF and biofuels On track - In the FY24 Annual Report, management entered a non-binding Term Sheet with Praj Industries for a 50:50 JV in India for SAF and other biofuel plants including ethanol, CBG, biodiesel and bio-bitumen. IndianOil and Praj signed the term sheet on 6 July 2023 to advance biofuels production capacity plans; no read yet on JV formation or plant development.
  28. NTPC Green Energy JV - \~2 GW renewable capacity On track - In the FY23 Annual Report, management stated that through collaboration with NTPC Green Energy Limited, the company is poised to augment renewable energy capacity by approximately 2 GW. The 2 GW NTPC JV renewable power is expected to be available in the next 5-6 months, while IOC NTPC Green Energy Pvt. Ltd. is on course to commission 50 MW of RE capacity this year.
  29. Motihari-Amlekhganj products pipeline - first transnational pipeline Delivered - In the FY20 Annual Report, management noted the Motihari-Amlekhganj products pipeline, the first transnational pipeline of the country. It was commissioned in July 2019, eight months ahead of schedule.
  30. MoPNG-Ministry of Shipping MoU - four MR vessels procurement On track - At the Q1 FY27 call, management stated that under the MoPNG-Ministry of Shipping MoU (signed 19th September, non-binding), Indian Oil shall explore procuring four MR vessels to start with, with tenders already out. By Q2 FY27 the board had approved buying a few vessels, with vessel purchase tenders out in the market a few months back.
  31. Pipeline projects - ₹35,000 crore, completion by February 2026, 21,298 km network Partial - In the FY23 Annual Report, management stated pipeline projects worth approximately ₹35,000 crore were under execution for completion by February 2026, taking the network to around 21,298 km and capacity to 164.37 MMTPA (liquid) and 50.73 MMSCMD (gas). The pipeline network spanned 20,009 km as of 31 March 2026, short of the 21,298 km target; no read on the specific project completion or capacity figures.
  32. LOBS production - CIDW units at Haldia and Gujarat, 530 TMT LOBS plant at Panipat Partial - In the FY23 Annual Report, management stated upcoming CIDW units at Haldia and Gujarat refineries would boost LOBS production and cut India's import dependence by almost 25%, with a 530 TMT LOBS plant being set up at Panipat Refinery. The Catalytic Dewaxing Unit-II at Haldia was commissioned in March 2024; no read on the Gujarat CIDW or the Panipat LOBS plant.
  33. IndianOil-Sun Mobility battery swapping JV - ₹1,800 crore equity infusion till FY27 Pending - In the FY23 Annual Report, management committed equity infusion of ₹1,800 crore in the 50:50 IndianOil-Sun Mobility battery swapping JV till financial year 2026-27, with Board approval for ₹640 crore in IOCL Singapore Pte. Ltd. for Sun Mobility preference shares and warrants. No read on equity infusion progress is available in our record.
  34. Group refining capacity - over 26 MMTPA addition to \~107 MMTPA "in the near future" On track - In the FY23 Annual Report, management committed over ₹1 Lakh Crore to strategic brownfield expansions, augmenting refining capacity by over 26 MMTPA to about 107 MMTPA "in the near future". Panipat (15→25), Gujarat (13.7→18) and Barauni (6→9) expansions totalling 16.3 MMTPA are underway, and the Guwahati expansion (1.0→1.2) was completed in November 2023; no read on Cauvery Basin Refinery progress.
  35. EV charging stations - 5,500 to 10,000 "in near future" Delivered - In the FY23 Annual Report, management targeted increasing EV charging stations from close to 5,500 to 10,000 "in near future". In FY26, EV charging/battery-swapping facilities stood at over 15,000 locations, with 15,040 stations as of FY26.
  36. Green Hydrogen plant at Panipat - 10 KTA (\~85 MW) On track - In the FY23 Annual Report, management planned a 10 KTA (\~85 MW) Green Hydrogen plant at Panipat, with Board-approved JVs with ReNew and L&T for green hydrogen production and electrolyzer manufacturing. Construction commenced after the LOA issued 26 June 2025 to L&T Energy Green Tech Ltd. on a BOO basis with a 25-year long-term supply arrangement.
  37. Polyester yarn and fibre facility at Bhadrak, Odisha Pending - In the FY23 Annual Report, management planned an upcoming polyester yarn and fibre production facility at Bhadrak, Odisha. No read on the Bhadrak facility's progress is available in our record.
  38. Styrene unit - 387 KTA at Panipat Pending - In the FY23 Annual Report, management planned to implement a 387 KTA Styrene unit at Panipat. No read on the Styrene unit's progress is available in our record.
  39. Digboi refinery expansion - 0.65 to 1 MMTPA Pending - In the FY23 Annual Report, management included the Digboi expansion from 0.65 to 1 MMTPA in its strategic brownfield capacity expansion plan. No read on the Digboi expansion's progress is available in our record.
  40. Cauvery Basin Refinery - 9 MMTPA greenfield at Nagapattinam Pending - In the FY21 Annual Report, management planned a 9 MMTPA greenfield Cauvery Basin Refinery at Nagapattinam in JV with CPCL, reiterated in the FY23 Annual Report. No read on the project's progress is available in our record.
  41. Capex plan - \~₹1 Lakh Crore over 4-5 years for refinery expansion Pending - In the FY21 Annual Report, management committed close to ₹1 Lakh Crore over the next four to five years for refinery expansion with petrochemical and lube integration plus other approved capex. FY24 capex was ₹42,236 crore and FY26 capex ₹32,405 crore (provisional), but FY22-FY23 and FY25 capex are not cited, so the cumulative ₹1 Lakh Crore outcome remains unverified; Panipat, Gujarat and Barauni expansions (gross approved cost ₹38,231, ₹18,936 and ₹18,113 crore) are 92.8%, 87.8% and 90.5% complete.
  42. 2G ethanol plant at Panipat - 2.4 KLPD fuel grade ethanol Delivered - In the FY21 Annual Report, management stated the 2G ethanol production plant at Panipat refinery, based on indigenous R&D technology (2.4 KLPD fuel grade ethanol), was set to be commissioned. The plant was dedicated to the nation on 10 August 2022, designed to utilise 2 lakh tonnes of rice straw to generate 3 crore litres of ethanol annually.
  43. 3G ethanol plant at Panipat - 35 KTA commercial scale, commissioning 2021-22 Partial - In the FY21 Annual Report, management stated the world's first 3G ethanol unit from refinery off-gas, via the LanzaTech gas fermentation partnership at a commercial scale of 35,000 tonnes/year, would be commissioned at Panipat in 2021-22. A 3G ethanol plant of 128 KLPD capacity was set up using refinery off gases; the commissioning date and 35 KTA scale are not confirmed in our record.
  44. Guwahati refinery expansion - 1.0 to 1.2 MMTPA Delivered - In the FY21 Annual Report, management planned the Guwahati refinery expansion from 1.0 to 1.2 MMTPA. The expansion was commissioned in November 2023.
  45. Paradip Petrochemical Complex - ₹61,000+ crore investment On track - In the FY23 Annual Report, management stated March 2023 Board 'Stage-I' approval for a Petrochemical Complex at Paradip, Odisha, at an estimated cost of over ₹61,000 crore, the largest-ever IndianOil investment at a single location, reiterated in the FY24 Annual Report. Paradip naphtha cracker Stage 1 board approval is in place with configuration studies and detailed engineering ongoing; 2,200 acres of land were approved by the Government of Odisha, of which 800 acres are notified.
  46. Ethanol blending - 10% target in ESY 2021-22 Delivered - In the FY23 Annual Report, management noted the target of 10% Ethanol Blending on industry basis in ESY 2021-22. The 10% target was achieved five months ahead of schedule, with 11.6% blending till March 2023 in ESY 2022-23.
  47. Capex target - ₹30,395 crore for FY24 Delivered - In the FY23 Annual Report, management targeted capex of ₹30,395 crore for 2023-24. FY24 cumulative capex came in at ₹42,236 crore, surpassing the budgeted target by over 139%.