- 2G Ethanol Plant - 60 KLPD at Harihara, Davangere
Pending - MRPL announced a 60 KLPD 2G Ethanol Plant at Harihara, Davangere using Corn Cob & Cotton Stock as feed, with a non-binding MOU signed with Mitsui and land allotted by KIADB; at the Q4 FY24 call the Board asked management to examine options to make the project more viable, with no timeline or capex committed. No construction or commissioning has been read in our record through Q2 FY27, with viability still under review as of Q4 FY24.
- Dividend - ₹700 crore average annual FY27-FY29
On track - Fitch rating commentary at the 29th September 2026 announcement indicated average annual dividend payment of ₹700 crore over FY27-FY29, with FY26 dividend at ₹700 crore. The Board declared a Q2 FY27 interim dividend of ₹3 per share totalling ₹526 crore, against the FY26 interim of ₹4 per share with payout of ₹701.04 crore.
- Drive Conversion of Turbines - executed during September 2028 shutdown
Pending - In the FY26 annual report, MRPL planned conversion of three compressor drive turbines (approved cost ₹206 crore) to be executed during the planned shutdown in September 2028. No read yet; the September 2028 shutdown has not been reached.
- Retail outlets - 250 by March 2025
Missed - In the FY22 annual report, MRPL stated it presently had 35 retail outlets and intended to have nearly 250 retail outlets by March 2025. The network stood at 167 outlets as on 31st March 2025, and reached 252 outlets as on 31st March 2026.
- Devangonthi Marketing Terminal - completion by October 2023 / Q3 FY24
Partial - The FY22 annual report stated the marketing terminal project at Devangonthi, on completion by October 2023, would propel MRPL's marketing expansion plans; the FY23 annual report said the project was progressing well and expected to be completed by Q3 of FY 2023-24. The terminal was commissioned in FY25 and became fully operational in FY26.
- Devanagunti-Bangalore Airport ATF pipeline - completed by FY29-30, ₹200 cr+
Pending - At the Q2 FY27 call, management stated the Devanagunti to Bangalore Airport ATF pipeline, with PNGRB authorization granted, is expected to be completed by year 29-30 at a cost of ₹200 crore plus. PNGRB has granted authorization to MRPL for the pipeline; no construction progress has been read.
- CHT unit restoration - mid-December 2026
Pending - At the Q2 FY27 call, management targeted restoration of the CHT (coker hydro treater) unit by mid-December 2026 following the 30th September 2026 fire, and expected Q3 throughput close to Q2 levels. Reconstruction has commenced, with a provisional loss of ₹118.76 crore booked as an exceptional item, and Q3 impact on total production expected to be less than a couple of percentage points; no restoration completion has been read.
- Debt reduction in Q4 FY26
Delivered - At the Q3 FY26 call, management expected to reduce current debt further during Q4 FY26 if markets remain good, with debt at that point ₹9,290 crores. By Q2 FY27, borrowings had fallen by over ₹5,000 crore in six months to ₹9,245 crore at end of September, with debt of ₹9,245 cr as of 05 Nov 2026.
- Retail outlets - all to feature one alternate fuel option (CNG or EV charger)
Partial - At the Q2 FY26 call, ED Marketing stated all retail outlets will feature one alternate fuel option - CNG or an EV charger - with larger highway outlets to have larger charging stations in collaboration with other companies. FY26 saw 76 EV charging stations commissioned across HiQ outlets, against 252 outlets as of FY26 end; no CNG station count was disclosed.
- Green hydrogen plant - 500 TPA, completed by March 2027
On track - At the Q4 FY24 call, management said the green hydrogen project was board approved and would be implemented within the refinery with capex of about ₹50 crores; at the Q4 FY25 call the 500 tons per year unit was being retendered on a BOO basis, and the FY26 annual report targeted the 500 TPA plant (approved cost ₹56 crore) to be completed by March 2027. Bids were received and under evaluation at Q4 FY25; no completion read through Q2 FY27.
- SAF/Bio-ATF plant - 20 KLPD, ready by 2026-27 / January 2027
On track - At the Q4 FY24 call, management said the Bio-ATF project was board approved, with a 20 KLPD demo plant to be constructed within the refinery and Bio-ATF expected ready by 2026-2027 when SAF becomes mandatory for international flights; the FY26 annual report targeted mechanical completion of the 20 KLPD demo project (approved cost ₹364 crore) in January 2027. Design work on the co-processing route was completed in Q2 FY26; no mechanical completion or production read through Q2 FY27.
- Q3 FY26 crude processing above 4.43 MMT
Delivered - At the Q2 FY26 call, management expected Q3 crude processing to be above 4.43 MMT. Q3 FY26 press release throughput of 0.47 crore MT was net crude, while PPAC's 4.56 MMT was gross crude; Q3 FY26 revenue was ₹24,712 cr.
- Q2 FY26 GRM high single digit
Delivered - At the Q1 FY26 call, the CFO targeted GRMs in the high single digit range for Q2 FY26. The company discontinued published GRM reporting in Q2 FY26, with the CFO describing indicative GRMs as roughly double of the previous quarter's $3.88/bbl - around $7.76/bbl - and Q2 FY26 PAT was ₹627 cr.
- Q2 FY26 throughput above 4.3 MMT
Delivered - At the Q1 FY26 call, management expected throughput in Q2 FY26 to be above 4.3 MMT. Q2 FY26 crude and other feedstock throughput came in at 4.4 MMT.
- Isobutylbenzene (IBB) pilot plant - mechanical completion August 2025, trials September 2025
Partial - At the Q1 FY26 call, management expected the IBB pilot cum demo plant's mechanical completion by end of August 2025, with trial runs starting by the third week or end of September 2025; at Q2 FY26 mechanical completion was to be declared within the next week to 10 days, with commissioning and first trials confident by early-to-mid November. As of Q3 FY26 the plant was still in the pilot phase, a few years from commercialization, with no mechanical completion or trial run confirmation in our record through Q2 FY27.
- Gas consumption increase to 0.65-0.7 MMSCMD in FY26
Missed - At the Q4 FY25 call, management targeted gas consumption to increase to around 0.65 to 0.7 MMSCMD in FY26, from \~0.55 MMSCMD the previous year; at Q2 FY26 the outer limit was cited as \~0.7 MMSCMD, potentially up to as high as 1 MMSCMD with near-term modifications. The combined natural gas run-rate stood close to 0.5 MMSCMD at Q2 FY26, with LNG consumption relatively low in Q3 FY26 and RLNG processing curtailed in Q2 FY27 due to high spot prices.
- Debt-to-equity maintained around current levels (\~1) through FY26-27
Delivered - At the Q4 FY25 call, management expected debt-to-equity to be maintained at around current levels (close to 1) despite a ₹1,000 crore per annum capex plan for the next two years; the ratio of 1.08x at Q1 FY26 was expected to improve, and stood at 0.63 by Q3 FY26. Debt-equity improved from 1.01 at end March '26 to 0.55 at September '26 end, at 0.54 as of 05 Nov 2026.
- FY26 GRM guidance - $6-6.5 per barrel
Delivered - At the Q4 FY25 call, management expected FY25-26 GRMs in the range of around $6 to $6.5 per barrel, similar to Q4. FY26 GRM came in at US$ 9.22 per barrel versus US$ 4.45 per barrel in the prior year; published GRM reporting was discontinued from Q2 FY26.
- Retail sales volume - 300 TKL FY26; 500 TKL FY27
Delivered - At the Q4 FY25 call, management set an FY25-26 retail outlet sales target to cross 300 TKL, versus \~230 TKL done in FY24-25; at Q1 FY26 the target was refined to around 300 to 325 TKL in FY26, with an FY27 target of about 500 TKL once \~270-300 outlets are in place. FY26 retail MS and HSD sales reached 34.39 crore litres, or 343.9 TKL, and Q2 FY27 retail product sales grew almost 50% YoY; no FY27 full-year figure yet.
- Retail outlet additions - 150 in FY26; network 330-340 by end FY26
Partial - At the Q4 FY25 call, management targeted 150 retail outlet additions in FY26, taking the network to around 330-340 outlets by end of year; the plan was scaled to about 100 additions and closer to 300 outlets at Q1 FY26, then to crossing 250 by end of year at Q2 FY26 and around 250 within FY26 at Q3 FY26. FY26 delivered 85 new retail outlets commissioned, for a total of 252 operational outlets as on 31st March 2026.
- Throughput \~1.7 crore tons FY26; >100% capacity utilization
Delivered - At the Q4 FY25 call, management targeted throughput of around 1.7 crore tons for FY26, operating at more than 100% capacity utilization. The refinery processed 16.774 MMT of crude oil in FY26 at 111.8% capacity utilisation, despite the planned shutdown of Phase-II Refinery Complex in April-May 2025.
- Fuel and loss reduction - 0.3-0.4% over 18-24 months; \~10% FY26; 9.5-10 target
Delivered - At the Q4 FY25 call, management expected fuel and loss to come down by around another 0.3% or 0.4% over the next 18 to 24 months via the grid power infrastructure project, targeting around 10% for the rest of FY26 and 9.5-10 for the next fiscal year. Fuel and loss fell from 10.42% in FY25 and 10.06% in Q3 FY26 to 9.86% in H1 FY27.
- Grid power upgradation project - commissioned by '25-'26 / December 2025 / mid-2026
Partial - At the Q4 FY24 call, management said the grid power upgradation project, coming up in '25-'26, would import grid power and reduce captive power; the completion target was December 2025 at Q4 FY25, revised at Q2 FY26 to commissioning by middle of next year and in the FY26 annual report to mechanical completion of balance activities by September 2026 (₹385 crore approved cost). As of Q2 FY27, grid power is not yet fully available and is expected by financial year end, with fuel and loss brought down below 10 and increased grid connectivity aimed for FY27.
- Routine capex \~₹1,000 cr annually FY25 and FY26
Partial - At the Q4 FY24 call, management guided routine capex of around ₹1,000 crores annually for FY25 and FY26, moving to "₹3,000 crores plus" annually with petchem projects; the FY26 target was revised to around ₹1,500 crores by Q2 FY26 and Q3 FY26, and Q2 FY27 guided FY26-27 capex in the range of ₹1,200 to ₹1,500 crore. Q1 FY26 capex was ₹537 crores and 9M FY26 capex ₹887 crores; CWIP moved FY25 729 → FY26 897 → 931 currently, with no full FY26 or FY27 capex actual disclosed.
- Retail outlets - 1,000 by FY26-27, sales 0.1 crore MT
On track - At the Q4 FY24 call, management set a retail outlet target of 1,000 outlets by '26, '27, with sales of 0.1 crore metric tons through these outlets; the target was progressively revised to \~500 outlets by FY 2028 end at Q2 FY27 and doubling to 500 by FY29. The network grew from 101 outlets in FY24 to 252 in FY26 and 257 at Q2 FY27, with retail sales of 34.39 crore litres in FY26; no 0.1 crore MT sales figure has been disclosed.
- Petchem intensity 10% → 12.5% - ₹8,000 cr over five years
On track - At the Q4 FY24 call, management planned new projects to enhance petchem intensity from the current 10% to 12.5%, with investment of approximately ₹8,000 crores over the next five years, primarily funded through internal accruals; board approval was expected around Q3 of that year. As of the FY26 annual report, petrochemical opportunities remain under evaluation rather than implementation, with the Phase 4 final report under review at Q2 FY26 and the OPML marketing JV formed in H1 FY27; no intensity figure or project approval has been disclosed through Q2 FY27.
- Throughput >1.7 crore metric tons in FY25 - no planned shutdowns
Delivered - At the Q4 FY24 call, management targeted throughput in excess of 1.7 crore metric tons in FY25 with no planned shutdowns, aligning with the focus on maximising asset utilisation. FY25 crude throughput came in at 1.8 crore tons (18.04 MMT) - 120% of nameplate capacity, a new record.