Reliance Industries Ltd Guidance Report - SOIC x StockScans Report
as of Nov 2026
- Jio capex tapering - 5G and UBR core network deployment essentially complete
Delivered - At the Q2 FY27 call, management said capex had started tapering, with 5G and UBR core network deployment essentially complete nationally. Q2 FY27 results confirmed the capex tapering.
- Jio-bp Pulse scaled to 1,100+ locations
Delivered - At the Q2 FY27 call, Jio-bp Pulse was presented as scaled to 1,100+ locations with 95% uptime and 50% YoY B2C sales growth. Q2 FY27 disclosures confirm Jio-bp Pulse at 1,100+ locations.
- PET recycling capacity more than doubling to 500 crore bottles
Pending - RIL announced a recycled PSF manufacturing facility in Andhra Pradesh to more than double its recycling capacity to 500 crore post-consumer PET bottles. FY23 saw 22.9 KT of PET recycled and FY26 29,000+ MT of plastics recycled, with no disclosed update on the Andhra Pradesh facility or the 500 crore bottle capacity.
- 7-Eleven stores - scale across India
Missed - At the October 2021 announcement, the first 7-Eleven store was launched in Mumbai with plans to scale it across the country. By Q2 FY27 the 7-Eleven format had been shut down, with a ₹108 crore exceptional charge taken.
- R-Cluster plateau production of about 12.8 MMSCMD in 2021
Delivered - In the FY21 annual report, the R-Cluster field was expected to reach plateau gas production of about 12.8 MMSCMD in 2021. R-Cluster achieved plateau production of \~12.8 MMSCMD in mid-April 2021, ahead of plan.
- Refining margins structurally likely to remain reasonably strong
Delivered - At the Q4 FY26 call, management said refining is tight and cracks are "structurally likely to remain reasonably strong" for some time, reiterating in Q2 FY27 that margins are not going to normalize soon. By Q2 FY27, gasoline cracks were \~$25/bbl versus $8.4 average in Q2 FY26 - about 3x - with diesel \~3.5x and jet 3.7x, after Q1 FY27 moves of petrol $10→$26, gas oil $16→$63 and ATF $14→$62.
- Jio tariff - no immediate plans to change
Delivered - At the Q4 FY25, Q2 FY26 and Q3 FY26 calls, management said there were no current plans to change tariffs - "no immediate plans". Q1 FY27 ARPU of ₹215.6 (+₹7 YoY) and Q2 FY27 ARPU of ₹218.8 (+3.5% YoY) were both organic, with no tariff actions in the last 12 months.
- O2C chemical margin recovery over the next 4-6 quarters
Partial - In the Q4 FY25 PPT, management expected "Recovery in chemical margins over the next 4-6 quarters". Over that horizon margins were mixed - Q1 FY26 PE -1%, PVC +4%, polyester chain -9%; Q4 FY26 PE -4%, PP -28% - before polyester chain margins rose 17% in Q1 FY27 and 33% in Q2 FY27 while PP and PVC stayed weak.
- Multi-GW electrolyzer manufacturing facility by end 2026
Pending - RIL stated it was on track to establish a fully automated, multi-GW electrolyser manufacturing facility by end 2026, with an electrolyzer tie-up with Nel announced at the Q4 FY25 call. No commissioning of the electrolyser manufacturing facility has been disclosed (-).
- Consumer brands international distribution in select markets "in a pretty big way"
Delivered - At the Q4 FY25 call, management said exports were being started and distribution would be set up in select markets "in a pretty big way", with Q1 FY27 launches planned in Australia and African countries. By Q1 FY27 FMCG had a presence in 40+ international markets, and by Q2 FY27 Campa was launched in Coles and Woolworths in Australia, in Kenya, and expanded in UAE, Oman and Malaysia.
- SHEIN meaningful scale-up in FY26
Delivered - At the Q4 FY25 call, management said "This year is when we look at meaningful scale-up. We will also start advertising" for Shein in FY26. Shein, commercially launched February 2025 with 0.2 crore app downloads, grew to 0.65 crore installs by Q3 FY26, 11 Mn+ by Q4 FY26, and 3 crore+ installs in Q1 FY27.
- Retail quick commerce - sub-30-minute delivery via store network
Delivered - At the Q4 FY25 call, management outlined sub-30-minute delivery via the store network with dark stores to be set up; dark stores were being rolled out in top 10 cities by Q1 FY26. Coverage grew from 4,000+ pin codes and 2,000+ stores at Q4 FY25 to 5,000+ pin codes with \~600 dark stores by Q2 FY26 and 5,100+ pin codes with daily orders +300% YoY by Q4 FY26.
- AI data centers - first phase evolving to a little over 100 MW over next two years
On track - At the Q2 FY26 call, management said the GCP region project's first phase "will evolve into little over 100 megawatt over the next two years", with gigawatt-scale data centres being worked towards by Q4 FY26. Q1 FY27 brought a Meta/Jio 168 MW data center in Jamnagar with a clear commissioning timeline, and by Q2 FY27 44 MW was "in the process of getting it done" with another 120 MW planned.
- O2C operating rates high and feedstock optimization
Delivered - At the Q1 FY27 call, management stated the plan to keep operating rates high, source crude globally, and that petchem production had already started to increase. The refinery ran at almost full capacity (\~96-97% throughput) in Q1 FY27 while rest of Asia ran 15-20% lower, and Q2 FY27 saw record crude runs despite Strait of Hormuz disruptions.
- KG-D6 ceiling price trending up to $9.9 in H2 FY27
Delivered - At the Q1 FY27 call, management expected the KG-D6 ceiling price (then $8.9) to trend up by at least $1 toward $9.9 in the second half of the year. In Q2 FY27 the KGD6 ceiling price was revised to $9.89/MMBtu for H2 FY27.
- KG-D6 rig arrival and multi-well exploration campaign
Delivered - At the Q1 FY27 call, management said the rig was arriving "next month" for initial exploration in the KG Basin, followed by a multi-year, multi-well campaign; a deep-water rig had been slated to arrive at KG-D6 in Q1 2026. By Q2 FY27 the deepwater rig was back in the KG-D6 block for workover and an additional development well campaign.
- Three new ethane VLECs delivered
Delivered - At the Q1 FY27 call, management said the first of three new VLECs was already delivered and loading at US ports, with the next two expected "in next couple of months"; the three carriers were ordered at Q4 FY25 with delivery from H2 2026. By Q2 FY27 the first was delivered and operating, the second was delivered and on its way to the US for its first load, and the third delivery was expected "very shortly".
- Fuel retail - no curtailments despite under-recoveries
Delivered - At the Q4 FY26 call, management said "we will not be making any curtailments" in domestic fuel marketing despite under-recoveries. RBML operated \~2,221 outlets in Q1 FY27 with retail prices not increased during the Strait of Hormuz closure, and Jio-bp added \~85-90 outlets in Q2 FY27 with growth in MS and HSD sales.
- Retail square footage and store count growth
Partial - At the Q4 FY26 call, management said "you should expect square footage to grow as well as number of stores to grow", with net area addition described as BAU in Q3 FY26. Retail reached 20,169 stores and 7.84 crore sq ft in Q1 FY27, but Q2 FY27 showed 19,947 stores and 7.75 crore sq ft - 222 stores lower - on underperforming store exits, with the format transition expected to take two-three quarters.
- Jio continuing to gain mobility market share
Delivered - At the Q4 FY26 call, management expected Jio to continue gaining market share in mobility. Jio reached 53.3 crore subscribers with 3.52 crore net adds in 12 months at Q1 FY27, and by Q2 FY27 had 54.2 crore subscribers with mobility net adds \~2x the industry.
- Jio ARPU growing 4-5% organically without tariff increases
Delivered - At the Q4 FY26 call, management expected ARPU to keep increasing even without tariff increases, continuing the observed 4-5% organic growth. ARPU was ₹214 (+4% YoY) in Q4 FY26, ₹215.6 in Q1 FY27 and ₹218.8 (+3.5% YoY) in Q2 FY27, all without tariff action.
- Retail doubling revenue every 3-4 years
On track - At the Q1 FY26 call, management reiterated the Chairman's AGM vision of doubling the retail business every 3 to 4 years - "we will potentially double in three years". FY26 retail gross revenue was ₹3,70,026 crore, up 12% YoY, with Q1 FY27 revenue of ₹90,000 crore (+7.4% reported) and Q2 FY27 +6.4% YoY - growth below the \~26% CAGR needed, though management reaffirmed the target in Q2 FY27.
- Doubling consolidated EBITDA over the next five years
On track - Management expressed confidence in doubling - indeed more than doubling - consolidated EBITDA over the next five years, reiterated at the Q1 FY26 call as "on track to double our value by the end of the golden decade". FY26 consolidated EBITDA was ₹2,07,911 crore, up 13.4%, with more than 2x growth from FY21 to FY26 already, and Q2 FY27 annualized EBITDA at ₹249,636 crore.
- 100 GW renewable energy capacity by 2030
On track - Reliance committed to establishing and enabling 100 GW of renewable energy capacity by 2030 in the FY26 annual report. The Kutch site spans 550,000 acres with technical potential of 125-150 GW peak solar, solar module production reached \~1 GWp by Q1 FY27 and module capacity 6+ GW by Q2 FY27.
- 44 MW data center completed in next four to six months
Pending - At the Q2 FY27 call, management said the 44 MW data center was "in the process of getting it done" within the next four to six months, with another 120 MW planned to "take some time". No completion has been disclosed; the Meta/Jio 168 MW Jamnagar data center carries a commercially sensitive commissioning timeline.
- Retail digital commerce accretive from FY28
On track - At the Q2 FY27 call, management said "this year is the year of investment", with benefits of digital commerce scale investment visible through FY 2028 and FY 2029 and online investments accretive to the bottom line from FY2028 onwards. Digital momentum is building - grocery digital orders +116% YoY in Q1 FY27, online grocery B2C revenue +42% YoY in Q2 FY27 - though retail EBITDA was down 10-11% YoY in Q2 FY27.
- Jio high-teens sustainable growth
On track - At the Q2 FY27 call, management saw visibility of high teen growth for Jio, with multiple monetization levers to drive sustainable high-teens growth. JPL EBITDA grew 16.6% YoY in Q2 FY27 and 17.9% in Q4 FY26, though revenue growth of 11.4-14.6% remains below high teens.
- O2C FY27 EBITDA of ₹80,000 crore annualized
On track - At the Q2 FY27 call, the O2C head reiterated being "well on the course to do exceedingly well in this year, Rs.80,000 Crores on the O2C basis", with the PPT showing H1 FY27 tracking annualized EBITDA of over ₹80,000 crore. O2C EBITDA was ₹17,010 crore in Q1 FY27 and ₹25,203 crore in Q2 FY27 - H1 of ₹42,213 crore, annualizing to \~₹84,000 crore.
- New Energy revenues from FY28
Pending - At the Q2 FY27 call, management stated the new energy earnings contribution would definitely start in FY 2028, with revenues from the new energy complex expected in FY2028. Module capacity is 6+ GW and solar cell nearing \~5 GW with ingot, wafer, polysilicon and glass progressing, but no revenue contribution has yet been recorded.
- Kutch renewable power supply beginning this year
On track - At the Q1 FY27 call, management said installation would start after the monsoons with power supply from Kutch to begin "this year" as the transmission network gets ready. By Q2 FY27, post-monsoon module installation had picked up pace with the first module not yet installed ("still on track"), transmission connectivity expected by Q1/first half of next calendar year, and 765 kV line construction underway since Q4 FY26.
- FMCG ₹1 lakh crore by FY30
On track - At the Q1 FY27 call, management reiterated the FMCG target - "the target continues... take this to INR1 lakh crores on FY30". RCPL revenue was ₹22,000 crore in FY26, ₹8,600 crore in Q1 FY27 (2.1x YoY) and ₹8,266 crore in Q2 FY27, with H1 FY27 at ₹16,900 crore, \~80% of last full year's revenue in six months.
- Retail doubling absolute EBITDA over three years
On track - At the Q1 FY27 call, retail management committed to doubling absolute EBITDA over three years - "a stretch" - reiterating in Q2 FY27 that "we are not changing ours, that is the target we are going for". FY26 retail EBITDA was ₹27,033 crore; Q1 FY27 EBITDA was "more or less flat", and Q2 FY27 EBITDA was ₹6,228 crore (7.8% margin, before a ₹108 crore 7-Eleven exceptional), with FY27 framed as investment-led and benefits accruing from next year.
- Jio IPO imminent - in the next few months
Delivered - At the Q3 FY26 call, management said the Jio IPO is "imminent now… it should happen in the next few months for sure", described as "fairly imminent" at Q4 FY26 and again at Q1 FY27. The Jio IPO completed and listed during the week of the Q2 FY27 call - India's largest IPO at ₹30,188 crore, listing at a 26.7% premium with market capitalisation of ₹13.1 lakh crore on day one.
- RCPL demerger completed effective 1 December 2025
Delivered - At the Q2 FY26 call, management said NCLT approval had come through and the demerger would happen in November 2025, pending the written judgment. RCPL became a direct subsidiary of RIL from 1 December 2025, confirming completion.
- Jio 5G traffic to surpass 4G "very, very shortly"
Delivered - At the Q3 FY25 call, management said total 5G traffic on Jio's network would surpass 4G traffic "very, very shortly". 5G crossed 50% of wireless data traffic by Q2 FY26, reached 53% by Q3 FY26 and stood at 1.5x 4G traffic by Q1 FY27, after 45% at Q4 FY25.
- Retail reverting to industry-leading growth in two quarters
Delivered - At the Q2 FY25 call, management committed that retail's streamlining and calibrated B2B approach would work through "in the next two quarters", after which the business would "revert to our industry leading growth momentum". Q4 FY25 revenue rose 16% YoY with streamlining "pretty much done" after three quarters, followed by +11% in Q1 FY26 and +18% in Q2 FY26.
- Jio-bp fuel retail network expansion beyond 1,916 outlets
Delivered - At the Q4 FY25 call, management said "we will expand that network" beyond the current 1,916 outlets, with continued expansion in the coming year or more. The network grew from \~2,000 outlets in Q1 FY26 to 2,199 by Q4 FY26 and 2,304 by Q2 FY27.
- Campa and Independence each crossing ₹1,000 crore turnover in FY25
Delivered - At the Q3 FY25 call, management committed that each of the Campa and Independence brands individually "should cross Rs 1000 crores turnover in FY25". By Q3 FY26 four brands had crossed ₹1,000+ crore each with Independence above ₹1,500 crore, and by FY26 Campa stood at ₹4,700 crore (4th largest CSD brand) and Independence at ₹2,600 crore.
- Jio AI Cloud - beta launch then scale to every Jio customer
Delivered - At the Q2 FY25 call, management said JioAICloud would "launch a beta very quickly, and then commercial services thereafter", to be scaled "to every Jio customer" in the coming quarter. Jio AI Cloud launched as beta with 100 GB free in Q3 FY25, crossed 3.3 crore registered users by Q1 FY26, and the Google Gemini Pro offer went live to all unlimited 5G users by Q3 FY26.
- Battery giga-factory - 40 GWh commissioning starting 2026
On track - At the Q4 FY25 call, management guided that "in 2026, you will start seeing, starting with packs and then going to the cells", with later revisions moving to phased commissioning during FY26, 40 GWh "this year" at Q1 FY27, and by Q2 FY27 the BESS facility (pack and container up to 40 GWh) in the next half calendar year with cell capacity \~35-40 GWh late next calendar year. All production line equipment for cell, pack and ESS was on site by Q3 FY26, but no commissioning had been disclosed by Q2 FY27, with BESS pushed to the next half calendar year.
- Solar giga-factory - 10 GW by end 2025/early 2026, scaling to 20 GW
Partial - At the Q4 FY25 call, management guided 10 GW per annum solar capacity designed to scale quickly to 20 GW, with "by end of 2025, early 2026, all these factories will get commissioned and will start producing"; later revisions moved the 20 GWp target to "in next few quarters" and then module 20 GW "early next year" and cell 20 GW "sometime first half next year". By Q3 FY26 the company was "well on our track" to commission the 10 GW gigafactory; by Q4 FY26 only a number of module and cell lines were commissioned with polysilicon, ingot, wafer and glass still to come, and by Q2 FY27 module capacity was 6+ GW and cell nearing \~5 GW.
- O2C PVC and polyester expansion - EBITDA contribution from FY27-28
On track - At the Q3 FY25 call, management outlined 0.15 crore tons of PVC/CPVC capacity at Dahej and Nagothane, three more VLECs, and a million tons of specialty polyester with 0.3 crore tons of PTA, with PVC commissioning 2026-2027 and EBITDA contribution 2027-2028, and PVC targeted complete by calendar year end 2026. Construction commenced at Dahej and Nagothane with long-lead orders placed, and accelerated execution of vinyl and PTA projects was a key priority at Q4 FY26, with no disclosed commissioning update in Q2 FY27.
- CBM 40-well multilateral campaign - production ramp-up from Q4 FY24
Delivered - At the Q2 FY24 call, management guided that production ramp-up under the 40-well CBM program would commence from Q4 FY24, with balance wells online by year end delivering incremental 0.05 crore standard cubic meters per day. 34 of 40 wells were on stream by Q3 FY25 and the first campaign was completed by Q4 FY25 with per-well productivity up from \~4,000 to 12,000-13,000 standard cubic meters; the second campaign reached 37 wells completed, 35 on production, by Q2 FY27.
- Net debt-to-EBITDA below 1x sustained
Delivered - At the Q4 FY23 call, management reiterated focus on keeping net debt-to-EBITDA below 1x with superior investment-grade ratings, a sustained balance-sheet policy reiterated at Q4 FY24 when the level was \~0.65. The ratio has stayed below 1x in every reported quarter - \~0.59 in Q1 FY26, \~0.64 in Q4 FY26, 0.60x in Q1 FY27 and 0.47x in Q2 FY27, with D/E at 0.41.
- Jio AirFiber / home broadband - 10 crore homes connected
On track - At the Q4 FY23 call, Jio targeted AirFiber home broadband presence in as high as 10 crore homes over the coming two or three years, an ambition reiterated through Q1 FY26, when UBR made it "much more doable and in near time". Connected premises grew from \~1.2 crore at Q4 FY24 to 2.2 crore homes (0.95 crore AirFiber) at Q2 FY26 and 3 crore homes (1.51 crore AirFiber) at Q2 FY27.
- Jio 5G pan-India rollout complete by December 2023
Delivered - At the Q2 FY23 call, management guided a pan-India 5G rollout by end of FY24 (December 2023) as firm guidance, reiterated through Q2 FY24 with capex intensity to decline thereafter. By Q3 FY24, "Jio has completed the True 5G network rollout as promised well ahead of the schedule", with \~9 crore subscribers migrated to 5G and DoT testing completed in all circles by 11 August 2023.
- MJ (KG-D6) gas condensate field - first gas by end 2022, ramp to 30 MMSCMD
Partial - At the Q2 FY23 call, management said it was on track to commission the MJ field by year-end 2022 with first gas by end of year, taking RIL from 20% to 30% of India's gas production, with full 30 MMSCMD capacity expected "by sometime in FY24"; the commissioning was later moved to Q1 FY24. MJ was commissioned in Q1 FY24, two quarters late, with all eight wells on production and close to 30 MMSCMD by Q2 FY24 and KG-D6 at \~30 MMSCMD, contributing \~30% of India's domestic gas production, by Q3 FY24.